|
Water intake project costing $5,284,100 plus taxes and bonus nears completion
|
|
|
David Burnside, Director of Engineering Services, brought an update
to Council, October 6th, regarding the raw water intake project at
Southampton. 13/01/2009 04:24 PM |
"The off-shore part of the project must be completed by the extension deadline," explains Burnside, "and once it is, they will then have to pressure test the line. We hope to have the line operational by the end of November." The total amount for the project was approved at
$5,284,100 (+ taxes) plus a $250,000 incentive bonus. The incentive
payment was not tied to the September 30th deadline but, instead, for
completion within one construction season and, therefore, will be paid
to McNally upon completion.
|