Purpose | Outstanding Balance as of Dec 31, 2008 | Annual Repayment | Final Payment Date | |
| Sanitary Sewer System | Southampton Sewage System - paid for by sewer users | $620,471.00 | $113,037.36 | 2015 | |
| Waterworks System |
Saugeen Beach Road water main extension. Local improvement charge paid for by benefitting property owners |
$667,347.91 | $108,142.97 | 2013 | |
| Waterworks System | Water Treatment Plant Up-grades - paid for by water system users | $7,691,632.04 | $616,881.56 | 2027 | |
| Parks & Recreation | Includes: Harbour Electrical upgrades (paid for by boaters), Cameron Park Washroom Improvements, Colliseum Roof, Ice Resurfacer | $231,170.46 | $39,799.01 | 2016 | |
| Tile Drainage Loans | Paid for by benefitting property owners | $26,783.82 | $15,988.00 |
varies
|
|
| Totals | $9,237,405.23 | $893,848.90 | |||
|
Annual Debt Repayment Limit - provided by the Ministry of Municipal Affairs and Housing
|
$3, 080,178.00 |
||||