|
The town of Saugeen Shores held the second of its
mandatory public meetings on Saturday, June 20th at the Plex in Port
Elgin, regarding the proposed new sanitary sewer project for the
area north of the Saugeen River.
Application for funding, under the recent infrastructure stimulus
fund set up by the Federal and Provincial governments, was approved
for a total of more than $17 million. Each level of government
covers one-third of the cost with the remaining one-third to be
assumed by residents who will have no option but to link in to the
new sewer system should it be approved.
The
first of the two meetings was held Wednesday, June 17th with
close to 300 people attending at Southampton's Town Hall. Although
today's crowd was somewhat smaller, it was no less vocal with the
majority expressing disagreement with the project.
Although the meetings were to focus on the environmental aspects of
the project, residents attending expressed many concerns in several
areas. Apparently, the area in question north of the Saugeen River
has, according to a recent study by Gamsby & Mannerow, a consulting
engineering company authorized by the town, "experienced significant
development pressure and continues to evolve from a seasonal cottage
community on private services to include a growing number of more
permanent dwellings and commercial properties on partial urban
services".
Engineer John Slocum, explained to those attending that there were
alternatives when it comes to installing a sanitary sewage system,
besides doing nothing.
Alternative #1: (favoured)
Gravity Sewer collection system with two pumping stations and
forcemain to the existing sewage treatment plant located in
Southampton
Alternative #2:
Low pressure sewage collection system
-
requires pressurizing system and pumping stations to
delivery flows via forcemain to sewage treatment plant
-
similar capital cost as #1 for municipal portion
plus sewage pumps required by property owners
-
greater operating and maintenance costs
-
additional annual costs incurred directly by
property owners
Alternative #3:
Gravity sewage collection system to a new treatment plant
-
- two pumping stations required
-
capital costs and operating & maintenance costs
would be far greater for a new treatment plant compared with a
forcemain discharging to the existing treatment plant
-
screening, grit removal and a new outfall to Lake
Huron would be required for a new treatment plant
During 'question and answer' time, residents raised the
issue of septic systems and whether or not a study had specifically be
done to examine their capacity for providing adequate sewage breakdown
and containment.
Long-time resident, Norm Gurr, held up a bottle of water taken from the
Saugeen River. "All of this," he said, "is going into the Lake Huron.
Septic systems today have proven to be very efficient, where matter,
broken down by bacteria then passes into the ground to nourish plant
life. Show us that there is a problem with the septic systems and we'll
fix it. I hope and pray that Council does the right thing. The only way
to be a great council is to ask the people their opinions and then
listen to them."
One of the questions raised was the costs involved. Dave Burnside, head
of Engineering for the town, explained that they [the town] hoped to
have a better handle on things once all the information comes in.
Southampton resident, Archie Gillies, inquired as to the capacity of the
existing treatment plants today. Burnside replied that each of the
plants, Southampton and Port Elgin were at 60 to 65 per cent capacity
and, if the sewer system project goes through, the Southampton plant
will come up to 80 to 85 per cent capacity. "I don't know why the town
isn't looking at the Miramichi Bay area instead," said Gillies. "The
development there has been rapid and continues to be and the need is
definitely there to upgrade the sanitary sewer system, before the north
side of the river, I would think."
Some residents also raised the concern that the proposed project was
more about development than the environment and the cost that would
weigh heavily on those who were on fixed income and who could least
afford the approximate $12,000 that will be payable by each resident to
hook into the new system if it goes ahead. In addition several were
concerned that a sewer system, and proposed upgrades to roads/streets to
include curbs, gutters, storm water outlets and sidewalks will raise
property values resulting in heavier taxes and increased assessment.
The Town's Chief Administrator Officer [CAO], Ron Brown, who officiated
the meeting said that no decision has been made by council as yet. "We
have to wait until all the reports are in, then they are presented to
Council for approval. We have not started the design aspect nor have we
decided on a formula for payment. Although the two meetings held were
required by law, residents asked that an additional meeting be
considered once all information is in regarding dollar figure for the
proposed figure.
At the end of the question and answer period, Mayor Mike Smith explained
that the town was not yet sure that the project would be considered to
go ahead. "We want to her from the people and I absolutely agree that we
don't have enough information to make a decision. Council and staff have
done everything they can to mitigate costs. Vice-Deputy Mayor, Doug
Gowanlock, also confirmed no decision has as yet been made about the
project however, he did say that as a municipal government, they wanted
to expand services as far as they could. "I would also like to encourage
people to attend council meetings that are open to the public."
Along the same vein, Councillor Victoria Serda, also encouraged people
to become more engaged in the political process insofar as it especially
involves their own community. "One of the problems," said Serda, "is
that the funding for this and other projects require a two-week time
frame. It also required that the project be one that is shovel ready and
one that hadn't been considered for the next two years. In other words,
we had to put forward projects that we didn't even know how the people
would feel about."
Serda also reminded everyone that it was their civic responsibility, as
a community, to become more engaged in the political process. "Part of
this is about caring about who you elect. You elect council but it's
vital that we get your feedback.", as she encouraged everyone to submit
the information feedback forms.
As more studies are completed, the town will be updating their on-line
site. It is anticipated that, should the project receive the blessing of
council, things will not be finalized until late fall.
(next column)

21/06/2009 12:53 AM
|

Town CAO, Ron Brown, answers questions

Engineer John Slocum fields technical questions

Residents line up to express dissatisfaction with
proposal
Long time resident Archie Gillies tries to come up with solutions

To make a point, Norm Gurr brings sample of water
taken from the mouth of the Saugeen River

Mayor Mike Smith explains town position on project
funding
 |