Goderich Street Reconstruction August 11, 2008

The southern section of Goderich Street, from Country Road 25 (CAW Rd.) to Barnes Avenue, including the Lake Ridge Drive intersection, will be undergoing reconstruction to accommodate the traffic issues that will result from the new Smart Centres Shopping Complex.

Although four contractors took out tenders for the project, none were received back by the town by the closing date of July 29th at 2:00 p.m.

Apparently, there was some confusion in the submission of a tender by Harold Sutherland Construction Ltd., the company that is doing the work for Smart Centres with it being delivered to the wrong location, in the wrong envelope and prior to the deadline.

(next column)

(continued)

 According to the Town's Purchasing Policy however, in such a situation, the Acting CAO can authorize the town's Department Head to enter into negotiations, which is what has taken place.

Therefore, Harold Sutherland Construction Ltd. has been awarded the tender in the amount of $491,483.00 plus applicable taxes. It is anticipated that project will take six to seven weeks for completion and will begin sometime after Labour Day in September.