|

A crane moves steel along the west side of the bridge
Work on the Huron Terrace bridge in Kincardine has increased by
another $70,000.
Public works manager Jim O'Rourke told Kincardine council Wednesday
night (June 10) that there is a problem with a sanitary sewer
forcemain located on the construction site. "Due to its location and
the close proximity of construction activities, there are concerns
that the forcemain pipe could rupture at any time," he said. "The
resulting spill of raw sewage to the environment, given the duration
of the event and the quantity of sewage involved, would be nothing
short of a disaster." (next column)

12/06/2009 12:13 AM
 |
O'Rourke said the work is tentatively scheduled for next
week and the cost is estimated at $70,000. That cost could be split
between the municipality (40%) and Bruce County (60%), based on
negotiations with the municipal and county engineers.
"How much is the engineering firm putting toward this mistake?" asked
councillor Randy Roppel. "This project is going to end up as a
nightmare."
O'Rourke said there is a contingency fund of $100,000 which will cover
this cost, and that's a lot better than having 200,000 gallons of raw
sewage spill into the environment. "Things come up in a project that you
don't see in advance," said councillor Ron Hewitt.
O'Rourke said the current forcemain is 60 years old so new pipes would
have been installed eventually anyway. Council approved the work.
The bridge was closed in May for construction of the new $4-million
structure, through a joint project between Kincardine and the county.
The project came in over-budget by $264,000 for Kincardine's portion
when it was announced in April. The municipality is paying 40 per cent
of the overall road and bridge work plus 100 per cent of the cost for
sanitary sewer and watermain work. The original budget for Kincardine
was $1.276 million, while the actual figure is $1.54 million.
 |